1 00:00:05,670 --> 00:00:11,499 [Music] 2 00:00:16,970 --> 00:00:14,539 Saturn five quarterly film report number 3 00:00:28,009 --> 00:00:16,980 fourteen covers progress during the 4 00:00:30,500 --> 00:00:28,019 period March April and May 1966 inside 5 00:00:32,810 --> 00:00:30,510 the 48 stories tall vertical Assembly 6 00:00:35,389 --> 00:00:32,820 Building at launch complex 39 of the 7 00:00:38,060 --> 00:00:35,399 Kennedy Space Center a mammoth and 8 00:00:40,400 --> 00:00:38,070 historic undertaking Assembly of the 9 00:00:43,549 --> 00:00:40,410 first complete Saturn 5 space vehicle 10 00:00:45,139 --> 00:00:43,559 began on March 15th with erection of the 11 00:00:47,869 --> 00:00:45,149 vehicles first stage on a mobile 12 00:00:48,889 --> 00:00:47,879 launcher from which future Saturn fives 13 00:00:51,200 --> 00:00:48,899 will be fired 14 00:00:52,880 --> 00:00:51,210 the initial vehicle will be used in 15 00:00:54,740 --> 00:00:52,890 checking out launch facilities and 16 00:00:57,410 --> 00:00:54,750 ground support equipment at the launch 17 00:00:59,450 --> 00:00:57,420 complex the first stage was built by the 18 00:01:03,619 --> 00:00:59,460 Boeing Company at Marshalls masu 19 00:01:06,200 --> 00:01:03,629 assembly facility in New Orleans on 20 00:01:08,750 --> 00:01:06,210 March 25th the next phase of the complex 21 00:01:10,340 --> 00:01:08,760 assembly operation was accomplished with 22 00:01:12,130 --> 00:01:10,350 the second stage of the facility's 23 00:01:14,570 --> 00:01:12,140 checkout vehicle moved into place 24 00:01:17,690 --> 00:01:14,580 hoisted by crane above the first stage 25 00:01:19,520 --> 00:01:17,700 and made it to it this stage was built 26 00:01:21,920 --> 00:01:19,530 by the space & Information Systems 27 00:01:25,969 --> 00:01:21,930 Division of North American Aviation at 28 00:01:28,010 --> 00:01:25,979 seal Beach California erection and 29 00:01:30,499 --> 00:01:28,020 mating of the third stage was performed 30 00:01:32,749 --> 00:01:30,509 on March 29th the Douglas Aircraft 31 00:01:35,179 --> 00:01:32,759 Company produced the facilities checkout 32 00:01:39,140 --> 00:01:35,189 stage at its Huntington Beach facility 33 00:01:41,300 --> 00:01:39,150 in California the facility's checkout 34 00:01:43,190 --> 00:01:41,310 instrument unit manufactured by 35 00:01:45,530 --> 00:01:43,200 International Business Machines at its 36 00:01:48,160 --> 00:01:45,540 facility in Huntsville Alabama was 37 00:01:50,719 --> 00:01:48,170 joined to the third stage on March 30th 38 00:01:53,359 --> 00:01:50,729 during April NASA and contractor 39 00:01:55,609 --> 00:01:53,369 engineers and technicians were busy 40 00:01:58,039 --> 00:01:55,619 installing various dummy ordnance items 41 00:02:00,800 --> 00:01:58,049 such as ullage and retro rockets and 42 00:02:04,399 --> 00:02:00,810 checking out GSE inside the vertical 43 00:02:05,929 --> 00:02:04,409 Assembly Building and on May 2nd mating 44 00:02:08,960 --> 00:02:05,939 of the facilities check out Apollo 45 00:02:11,869 --> 00:02:08,970 spacecraft built by North Americans S&I 46 00:02:13,870 --> 00:02:11,879 D marked completion of assembly of the 47 00:02:18,280 --> 00:02:13,880 first Saturn 5 vehicle 48 00:02:21,100 --> 00:02:18,290 on May 25th the vehicle standing 350 49 00:02:23,500 --> 00:02:21,110 feet tall was rolled out of the VAB to 50 00:02:25,990 --> 00:02:23,510 begin its maiden journey requiring six 51 00:02:30,280 --> 00:02:26,000 hours aboard the mobile launcher to pad 52 00:02:32,230 --> 00:02:30,290 39a three miles away test objectives for 53 00:02:34,270 --> 00:02:32,240 the facility's checkout vehicle include 54 00:02:36,940 --> 00:02:34,280 evaluation of launch vehicle assembly 55 00:02:38,560 --> 00:02:36,950 and handling operations evaluation of 56 00:02:41,290 --> 00:02:38,570 propellant and pneumatic servicing 57 00:02:43,510 --> 00:02:41,300 operations evaluation of compatibility 58 00:02:45,910 --> 00:02:43,520 of launch vehicle with GSE and 59 00:02:48,280 --> 00:02:45,920 facilities determination of vehicle 60 00:02:51,160 --> 00:02:48,290 response to ground wind conditions and 61 00:02:55,720 --> 00:02:51,170 training of personnel to process saturn 62 00:02:57,700 --> 00:02:55,730 v launch vehicles manufacturing and 63 00:02:59,430 --> 00:02:57,710 check out of first stages by the Boeing 64 00:03:03,310 --> 00:02:59,440 Company and the Marshall Center 65 00:03:06,040 --> 00:03:03,320 continued throughout the quarter in 66 00:03:07,810 --> 00:03:06,050 first stage ground test operations the 67 00:03:10,630 --> 00:03:07,820 upper assembly of the structural test 68 00:03:13,300 --> 00:03:10,640 stage comprising the inter tank LOX tank 69 00:03:15,400 --> 00:03:13,310 and forward skirt was installed in 70 00:03:18,100 --> 00:03:15,410 Marshalls load test tower in mid-april 71 00:03:20,710 --> 00:03:18,110 and prepared for structural tests due to 72 00:03:22,570 --> 00:03:20,720 start next quarter similar testing was 73 00:03:25,480 --> 00:03:22,580 successfully completed this quarter on 74 00:03:27,460 --> 00:03:25,490 the stages lower assembly comprising the 75 00:03:31,420 --> 00:03:27,470 thrust structure fuel tank and inner 76 00:03:33,340 --> 00:03:31,430 tank the first flight stage which was 77 00:03:35,950 --> 00:03:33,350 successfully static fired at Marshall 78 00:03:38,140 --> 00:03:35,960 last quarter underwent refurbishment and 79 00:03:40,450 --> 00:03:38,150 began post static checkout during the 80 00:03:43,500 --> 00:03:40,460 report period the stage will be shipped 81 00:03:46,360 --> 00:03:43,510 to the Kennedy Space Center in August 82 00:03:48,840 --> 00:03:46,370 the second flight stage was installed in 83 00:03:50,740 --> 00:03:48,850 Marshall static test and on May 17th 84 00:03:53,170 --> 00:03:50,750 following completion of post 85 00:03:55,360 --> 00:03:53,180 manufacturing check out a single 86 00:03:57,160 --> 00:03:55,370 acceptance static firing of a hundred 87 00:04:01,540 --> 00:03:57,170 and twenty five seconds duration is 88 00:04:03,550 --> 00:04:01,550 scheduled for the stage on June 7th at 89 00:04:06,070 --> 00:04:03,560 Marshalls miss shoe assembly facility in 90 00:04:08,890 --> 00:04:06,080 New Orleans Assembly of the third flight 91 00:04:10,630 --> 00:04:08,900 stage was completed on March 9th and the 92 00:04:12,850 --> 00:04:10,640 stage was moved into the stage test 93 00:04:15,550 --> 00:04:12,860 building for post manufacturing checkout 94 00:04:18,370 --> 00:04:15,560 this is the first flight stage assembled 95 00:04:20,020 --> 00:04:18,380 by Boeing Atmos you to ground test 96 00:04:22,750 --> 00:04:20,030 stages had previously been assembled 97 00:04:24,340 --> 00:04:22,760 there after completion of checkout the 98 00:04:26,440 --> 00:04:24,350 third flight stage will go to the 99 00:04:27,999 --> 00:04:26,450 Marshall Center for acceptance static 100 00:04:30,260 --> 00:04:28,009 firing 101 00:04:32,930 --> 00:04:30,270 vertical assembly of the fourth flight 102 00:04:34,460 --> 00:04:32,940 stage has been completed at masu this 103 00:04:36,860 --> 00:04:34,470 stage will be the first flight booster 104 00:04:39,080 --> 00:04:36,870 destined for acceptance static firing at 105 00:04:44,480 --> 00:04:39,090 Marshalls Mississippi test facility 106 00:04:46,550 --> 00:04:44,490 early in 1967 a new upper fuel tank 107 00:04:49,070 --> 00:04:46,560 bulkhead for the fifth flight stage has 108 00:04:51,200 --> 00:04:49,080 been welded into position to replace one 109 00:04:53,240 --> 00:04:51,210 which partially collapsed while being 110 00:04:56,150 --> 00:04:53,250 drained after hydrostatic testing on 111 00:04:58,339 --> 00:04:56,160 April 28th the collapse was caused by a 112 00:05:01,430 --> 00:04:58,349 negative internal pressure due to an 113 00:05:05,300 --> 00:05:01,440 improper test procedure no impact on the 114 00:05:07,580 --> 00:05:05,310 assembly schedule is foreseen structural 115 00:05:10,279 --> 00:05:07,590 assembly of major components for the 116 00:05:14,300 --> 00:05:10,289 sixth flight stage is now in progress by 117 00:05:16,700 --> 00:05:14,310 Boeing masu fabrication of components 118 00:05:25,390 --> 00:05:16,710 such as bulkhead Gore segments for the 119 00:05:29,930 --> 00:05:28,010 the first static firing test of the 120 00:05:32,300 --> 00:05:29,940 second stage flight wait all system 121 00:05:34,879 --> 00:05:32,310 stage was successfully held on April 122 00:05:37,670 --> 00:05:34,889 23rd at the Marshall centers Mississippi 123 00:05:39,709 --> 00:05:37,680 test facility running 15 seconds as 124 00:05:42,830 --> 00:05:39,719 scheduled the tests marked the first 125 00:05:52,040 --> 00:05:42,840 operational use of MTF NASA's newest 126 00:05:54,439 --> 00:05:52,050 facility the first full duration 355 127 00:05:56,390 --> 00:05:54,449 second static firing of the stage was 128 00:05:58,999 --> 00:05:56,400 successfully conducted on May 20th 129 00:06:01,640 --> 00:05:59,009 Jim willing of all four outboard j2 130 00:06:04,700 --> 00:06:01,650 engines was performed the full duration 131 00:06:07,189 --> 00:06:04,710 test had been preceded by a 150 second 132 00:06:09,830 --> 00:06:07,199 firing on May 17th following three 133 00:06:12,709 --> 00:06:09,840 earlier attempts in a second scheduled 134 00:06:14,300 --> 00:06:12,719 full duration firing on May 25th a fire 135 00:06:17,089 --> 00:06:14,310 developed around the number four engine 136 00:06:19,580 --> 00:06:17,099 recirculation valve burning until fuel 137 00:06:24,649 --> 00:06:19,590 was D tanked using the emergency dump 138 00:06:27,379 --> 00:06:24,659 system on May 28th an explosion of the 139 00:06:29,629 --> 00:06:27,389 stages liquid hydrogen tank occurred due 140 00:06:31,879 --> 00:06:29,639 to overpressure during a leak check test 141 00:06:34,999 --> 00:06:31,889 and the stage was almost completely 142 00:06:37,550 --> 00:06:35,009 destroyed pressurization was with helium 143 00:06:40,070 --> 00:06:37,560 and no liquid hydrogen was involved in 144 00:06:41,060 --> 00:06:40,080 the blow-up the tank was over pressured 145 00:06:43,060 --> 00:06:41,070 as a result of the 146 00:06:45,410 --> 00:06:43,070 pressure switches being disconnected and 147 00:06:47,720 --> 00:06:45,420 subsequent ground override of the stage 148 00:06:50,450 --> 00:06:47,730 and facility vent valves to obtain 149 00:06:52,880 --> 00:06:50,460 pressure during the leak check facility 150 00:06:54,740 --> 00:06:52,890 damage appears to be repairable prior to 151 00:06:57,160 --> 00:06:54,750 scheduled arrival of the first s to 152 00:06:59,900 --> 00:06:57,170 flight stage at MTF next quarter 153 00:07:02,800 --> 00:06:59,910 possible program impact due to the 154 00:07:05,390 --> 00:07:02,810 accident is under investigation 155 00:07:08,150 --> 00:07:05,400 the thrust structure assembly for the 156 00:07:10,370 --> 00:07:08,160 second stage high force test program was 157 00:07:13,040 --> 00:07:10,380 shipped in April from Essen IDs seal 158 00:07:15,500 --> 00:07:13,050 beach facility to the wiley laboratories 159 00:07:17,630 --> 00:07:15,510 in Huntsville Alabama where acoustical 160 00:07:21,530 --> 00:07:17,640 and mechanical vibration testing will 161 00:07:23,900 --> 00:07:21,540 get underway next quarter at North 162 00:07:26,900 --> 00:07:23,910 Americans Santa Susana California field 163 00:07:29,480 --> 00:07:26,910 laboratory to full duration firings of 164 00:07:31,940 --> 00:07:29,490 the second stage battleship stage using 165 00:07:34,370 --> 00:07:31,950 flight configuration j2 engines were 166 00:07:37,280 --> 00:07:34,380 held in March to complete the major test 167 00:07:39,200 --> 00:07:37,290 program of battleship development the 168 00:07:41,450 --> 00:07:39,210 battleship stage will be maintained in a 169 00:07:45,710 --> 00:07:41,460 minimum capability status to allow 170 00:07:47,930 --> 00:07:45,720 additional firings if needed work on 171 00:07:50,300 --> 00:07:47,940 second stage flight stages continued at 172 00:07:51,950 --> 00:07:50,310 seal beach with systems installation for 173 00:07:54,800 --> 00:07:51,960 the first flight stage completed in 174 00:07:57,800 --> 00:07:54,810 April systems check out now in progress 175 00:07:59,870 --> 00:07:57,810 will be finished June 30th and the stage 176 00:08:03,710 --> 00:07:59,880 will then be shipped to MTF for 177 00:08:05,180 --> 00:08:03,720 acceptance static firing pneumo static 178 00:08:06,560 --> 00:08:05,190 testing and cleaning of the second 179 00:08:08,300 --> 00:08:06,570 flight stage have been accomplished 180 00:08:11,030 --> 00:08:08,310 following completion of vertical 181 00:08:13,520 --> 00:08:11,040 assembly in April systems installation 182 00:08:17,390 --> 00:08:13,530 now underway is expected to be done by 183 00:08:19,550 --> 00:08:17,400 July Assembly of major structural 184 00:08:21,620 --> 00:08:19,560 components for the third flight stage is 185 00:08:25,340 --> 00:08:21,630 complete and the stages and vertical 186 00:08:27,770 --> 00:08:25,350 build-up for flight stages four through 187 00:08:37,460 --> 00:08:27,780 six fabrication and sub assembly of 188 00:08:41,899 --> 00:08:39,589 the first flight stage was shipped by 189 00:08:43,760 --> 00:08:41,909 ocean-going barge on March 11th from 190 00:08:46,460 --> 00:08:43,770 Douglas Aircraft company's Huntington 191 00:08:49,010 --> 00:08:46,470 Beach California facility and arrived 192 00:08:52,190 --> 00:08:49,020 four days later at Douglass's Sacramento 193 00:08:54,830 --> 00:08:52,200 test center for acceptance firing on 194 00:08:57,710 --> 00:08:54,840 March 21st the stage was installed in 195 00:09:00,020 --> 00:08:57,720 sac toes beta test and number one pre 196 00:09:02,600 --> 00:09:00,030 firing check-out began nine days later 197 00:09:05,210 --> 00:09:02,610 and the fully successful acceptance 198 00:09:08,480 --> 00:09:05,220 static firing test of 455 seconds 199 00:09:11,000 --> 00:09:08,490 duration was run on May 26 in the test 200 00:09:13,460 --> 00:09:11,010 the stage demonstrated the j2 engine 201 00:09:16,130 --> 00:09:13,470 restart capability after a simulated 202 00:09:19,190 --> 00:09:16,140 orbital Coast area the stage initially 203 00:09:21,050 --> 00:09:19,200 fired for 150 seconds then after restart 204 00:09:23,360 --> 00:09:21,060 for 305 seconds 205 00:09:30,170 --> 00:09:23,370 delivery of the first flight stage to 206 00:09:32,270 --> 00:09:30,180 KSC is scheduled for July factory 207 00:09:34,250 --> 00:09:32,280 checkout of the second flight stage was 208 00:09:36,530 --> 00:09:34,260 completed May 9th at Huntington Beach 209 00:09:39,740 --> 00:09:36,540 the stage is being prepared for shipment 210 00:09:42,200 --> 00:09:39,750 to Sacto on May 31st aboard the super 211 00:09:45,950 --> 00:09:42,210 guppy aircraft for acceptance firing 212 00:09:47,540 --> 00:09:45,960 scheduled in late July because of the 213 00:09:50,000 --> 00:09:47,550 requirement for assembly of a new 214 00:09:52,070 --> 00:09:50,010 hydrostatic test stage occasioned by 215 00:09:54,530 --> 00:09:52,080 damage to the third flight stages LOX 216 00:09:57,020 --> 00:09:54,540 tank during hydrostatic testing last 217 00:09:59,210 --> 00:09:57,030 quarter certain flight stage structural 218 00:10:01,490 --> 00:09:59,220 components are being interchanged to 219 00:10:04,130 --> 00:10:01,500 provide minimum overall scheduled impact 220 00:10:06,530 --> 00:10:04,140 the damaged LOX tank has been repaired 221 00:10:08,770 --> 00:10:06,540 and successfully retested and will be 222 00:10:11,410 --> 00:10:08,780 part of the new hydrostatic test stage 223 00:10:13,520 --> 00:10:11,420 structural fabrication is continuing on 224 00:10:17,900 --> 00:10:13,530 components for the fourth and fifth 225 00:10:19,730 --> 00:10:17,910 flight stages the s4b stage simulator 226 00:10:22,280 --> 00:10:19,740 was removed from the vehicle checkout 227 00:10:25,190 --> 00:10:22,290 tower at SAC tow in March following 228 00:10:26,960 --> 00:10:25,200 completion of factory checkout and was 229 00:10:29,540 --> 00:10:26,970 shipped by super guppy to the Marshall 230 00:10:32,240 --> 00:10:29,550 Center for use in its Saturn 5 systems 231 00:10:34,010 --> 00:10:32,250 development facility the stage simulator 232 00:10:36,590 --> 00:10:34,020 consists of a thrust structure and 233 00:10:41,000 --> 00:10:36,600 functional mock-up engine plus forward 234 00:10:42,980 --> 00:10:41,010 and aft skirts acceptance test firings 235 00:10:45,350 --> 00:10:42,990 of the auxiliary propulsion system 236 00:10:47,990 --> 00:10:45,360 modules for the first flight stage were 237 00:11:00,940 --> 00:10:48,000 held on May 6th and 13th at SAC tows 238 00:11:06,670 --> 00:11:04,420 all 5f1 engines for the fourth s1c 239 00:11:08,500 --> 00:11:06,680 flight stage plus three of the engines 240 00:11:10,210 --> 00:11:08,510 for the fifth flight stage were 241 00:11:10,810 --> 00:11:10,220 delivered by Rocketdyne during this 242 00:11:13,150 --> 00:11:10,820 quarter 243 00:11:15,490 --> 00:11:13,160 rocket Dean's nearly completed vertical 244 00:11:17,620 --> 00:11:15,500 assembly production line at the Canoga 245 00:11:20,200 --> 00:11:17,630 Park California plant is now in 246 00:11:22,570 --> 00:11:20,210 operation and producing f-1 engines at 247 00:11:24,640 --> 00:11:22,580 the rate of two a month engines 248 00:11:27,280 --> 00:11:24,650 delivered this quarter were of the qual 249 00:11:29,620 --> 00:11:27,290 two configuration qualified for manned 250 00:11:31,510 --> 00:11:29,630 flight reliability and designed to meet 251 00:11:33,790 --> 00:11:31,520 the additional payload requirements of 252 00:11:37,510 --> 00:11:33,800 the fourth Saturn 5 and subsequent 253 00:11:39,940 --> 00:11:37,520 vehicles an intensive f1 engine 254 00:11:42,130 --> 00:11:39,950 component qualification test program was 255 00:11:44,950 --> 00:11:42,140 continued by Rocketdyne throughout the 256 00:11:46,530 --> 00:11:44,960 report period this static load test of 257 00:11:49,110 --> 00:11:46,540 the hyper gal manifold assembly 258 00:11:51,820 --> 00:11:49,120 performed at zero degrees Fahrenheit 259 00:11:56,500 --> 00:11:51,830 simulates effects of engine storage at 260 00:11:57,970 --> 00:11:56,510 low temperature conditions in vibration 261 00:12:00,670 --> 00:11:57,980 testing of the flight instrument 262 00:12:02,860 --> 00:12:00,680 junction box stroboscopic photography 263 00:12:12,430 --> 00:12:02,870 transforms the action into slow-motion 264 00:12:14,830 --> 00:12:12,440 for engineering analysis a total of 12 265 00:12:17,110 --> 00:12:14,840 j2 engines was delivered by Rocketdyne 266 00:12:19,960 --> 00:12:17,120 this quarter including the first of the 267 00:12:21,820 --> 00:12:19,970 new upgraded 230,000 pounds thrust 268 00:12:24,070 --> 00:12:21,830 engines which went to the Marshall 269 00:12:26,530 --> 00:12:24,080 Center for static firing tests the 270 00:12:30,400 --> 00:12:26,540 engine has 5,000 pounds more thrust than 271 00:12:32,740 --> 00:12:30,410 previous j2 s rocket deans new j2 engine 272 00:12:34,840 --> 00:12:32,750 production line at the Canoga Park plant 273 00:12:37,360 --> 00:12:34,850 features positioning of engines at floor 274 00:12:40,630 --> 00:12:37,370 level to allow ready access by personnel 275 00:12:44,380 --> 00:12:40,640 also each engine can be rotated to the 276 00:12:46,480 --> 00:12:44,390 exact area desired a teardown 277 00:12:48,880 --> 00:12:46,490 engineering inspection was held in March 278 00:12:51,190 --> 00:12:48,890 on the j2 engine which had previously 279 00:12:53,740 --> 00:12:51,200 completed the qualification test series 280 00:12:55,330 --> 00:12:53,750 at Santa Susana all components were 281 00:12:57,880 --> 00:12:55,340 found to be in excellent condition and 282 00:13:00,730 --> 00:12:57,890 suitable for use after reassembly in 283 00:13:04,450 --> 00:13:00,740 either the spares support program or the 284 00:13:06,130 --> 00:13:04,460 research and development program at the 285 00:13:07,570 --> 00:13:06,140 Air Force's Arnold engineering 286 00:13:10,900 --> 00:13:07,580 development center at Tullahoma 287 00:13:13,240 --> 00:13:10,910 Tennessee the douglas s4 bead battleship 288 00:13:14,480 --> 00:13:13,250 stage to be used for tankage in a series 289 00:13:17,000 --> 00:13:14,490 of j2 engine 290 00:13:19,519 --> 00:13:17,010 environmental verification tests was 291 00:13:22,070 --> 00:13:19,529 installed in a test cell and the engine 292 00:13:24,380 --> 00:13:22,080 was mounted firing tests are scheduled 293 00:13:27,079 --> 00:13:24,390 next quarter for verification of start 294 00:13:36,350 --> 00:13:27,089 restart and performance at simulated 295 00:13:38,600 --> 00:13:36,360 high-altitude conditions the flight 296 00:13:41,360 --> 00:13:38,610 systems instrument unit assembled at 297 00:13:43,010 --> 00:13:41,370 MSFC was delivered in early March to 298 00:13:45,290 --> 00:13:43,020 Douglas Aircraft Huntington Beach 299 00:13:47,420 --> 00:13:45,300 facility where preparations were made 300 00:13:49,480 --> 00:13:47,430 for functional tests scheduled for late 301 00:13:51,650 --> 00:13:49,490 May in an environmental chamber 302 00:13:54,139 --> 00:13:51,660 simulating orbital thermal vacuum 303 00:13:57,019 --> 00:13:54,149 conditions during the vacuum environment 304 00:13:59,480 --> 00:13:57,029 test the IU will be mated with a third 305 00:14:03,710 --> 00:13:59,490 stage forward stage simulator and a 306 00:14:05,810 --> 00:14:03,720 lunar module thermal simulator vibration 307 00:14:08,120 --> 00:14:05,820 testing of the second vibration test IU 308 00:14:10,730 --> 00:14:08,130 was successfully conducted at Wiley labs 309 00:14:12,769 --> 00:14:10,740 Huntsville facility during April to 310 00:14:14,690 --> 00:14:12,779 verify the flight worthiness of the IBM 311 00:14:17,360 --> 00:14:14,700 produced unit for Saturn five vehicles 312 00:14:21,290 --> 00:14:17,370 with respect to specified vibration 313 00:14:23,990 --> 00:14:21,300 environments a third structure will test 314 00:14:27,670 --> 00:14:24,000 IU is now being built by IBM Huntsville 315 00:14:29,600 --> 00:14:27,680 scheduled for delivery to MSFC in June 316 00:14:31,490 --> 00:14:29,610 investigation of the crumpling of the 317 00:14:34,430 --> 00:14:31,500 second structure will test IU last 318 00:14:36,699 --> 00:14:34,440 quarter during load testing over the st1 319 00:14:39,500 --> 00:14:36,709 24 stabilized platform position 320 00:14:43,850 --> 00:14:39,510 indicated need for continuation of tests 321 00:14:46,220 --> 00:14:43,860 using a new IU component installation 322 00:14:48,889 --> 00:14:46,230 for the first Saturn five flight IU has 323 00:14:51,560 --> 00:14:48,899 been finished at IBM and check-out is in 324 00:14:57,190 --> 00:14:51,570 progress upon completion scheduled July 325 00:15:02,240 --> 00:14:59,569 structural fabrication of the second 326 00:15:05,120 --> 00:15:02,250 Saturn 5 flight IU which began March 327 00:15:06,800 --> 00:15:05,130 21st is nearing completion component 328 00:15:13,950 --> 00:15:06,810 installation is due to be finished in 329 00:15:18,360 --> 00:15:16,620 buildup of Marshall Saturn five systems 330 00:15:20,910 --> 00:15:18,370 development facility neared completion 331 00:15:23,010 --> 00:15:20,920 this quarter with installation of the 332 00:15:25,350 --> 00:15:23,020 third stage forward section with 333 00:15:27,420 --> 00:15:25,360 breadboard instrument unit attached plus 334 00:15:30,240 --> 00:15:27,430 the third stage aft section and j2 335 00:15:32,190 --> 00:15:30,250 engine the facility is a breadboard or 336 00:15:36,060 --> 00:15:32,200 simulation of launch vehicle automatic 337 00:15:38,790 --> 00:15:36,070 checkout GSE at launch complex 39 KSC 338 00:15:42,990 --> 00:15:38,800 Plus components simulating a completely 339 00:15:44,550 --> 00:15:43,000 assembled Saturn 5 vehicle installation 340 00:15:46,560 --> 00:15:44,560 and check-out of equipment around the 341 00:15:50,060 --> 00:15:46,570 interior circumference of the breadboard 342 00:15:52,050 --> 00:15:50,070 instrument unit is well underway 343 00:15:53,370 --> 00:15:52,060 installation of electrical support 344 00:15:56,370 --> 00:15:53,380 equipment is now complete in the 345 00:15:58,380 --> 00:15:56,380 breadboard areas simulating the LC 39 346 00:16:00,930 --> 00:15:58,390 launch control center and mobile launch 347 00:16:03,150 --> 00:16:00,940 facility ground equipment tests at the 348 00:16:05,250 --> 00:16:03,160 breadboard LCC were finished this 349 00:16:07,410 --> 00:16:05,260 quarter as well as debugging of the 350 00:16:09,270 --> 00:16:07,420 checkout tapes for use at KSC in 351 00:16:19,110 --> 00:16:09,280 checkout of the Saturn five facilities 352 00:16:22,470 --> 00:16:19,120 checkout vehicle at the Marshall centers 353 00:16:24,630 --> 00:16:22,480 Saturn 5 dynamic test and the Shakers 354 00:16:26,790 --> 00:16:24,640 which will vibrate the Saturn 5 dynamic 355 00:16:29,550 --> 00:16:26,800 test vehicle during dynamic testing this 356 00:16:31,980 --> 00:16:29,560 fall underwent acceptance testing during 357 00:16:34,560 --> 00:16:31,990 the quarter the shakers built by laying 358 00:16:36,480 --> 00:16:34,570 electronics Anaheim California were 359 00:16:39,120 --> 00:16:36,490 tested against a forty-seven thousand 360 00:16:41,610 --> 00:16:39,130 pound mass of steel mounted on wheels on 361 00:16:44,220 --> 00:16:41,620 a track three such shakers will be 362 00:16:47,600 --> 00:16:44,230 installed in the dynamic test stand one 363 00:16:50,850 --> 00:16:47,610 for lateral mode and two for roll mode 364 00:16:52,740 --> 00:16:50,860 the s2 facilities checkout stage will be 365 00:16:55,380 --> 00:16:52,750 shipped from KSC to Marshall in 366 00:16:57,570 --> 00:16:55,390 September for use as part of the dynamic 367 00:17:00,180 --> 00:16:57,580 test vehicle as a result of a decision 368 00:17:04,320 --> 00:17:00,190 in early May instead of using the all 369 00:17:06,270 --> 00:17:04,330 system stage as originally planned at 370 00:17:08,670 --> 00:17:06,280 Marshalls Mississippi test facility 371 00:17:11,010 --> 00:17:08,680 construction continued on second stage 372 00:17:14,760 --> 00:17:11,020 static tests and number two designated 373 00:17:17,070 --> 00:17:14,770 a1 while the first or a to stand became 374 00:17:19,980 --> 00:17:17,080 operational with the initial second 375 00:17:22,020 --> 00:17:19,990 stage all system stage firing a1 376 00:17:24,780 --> 00:17:22,030 superstructure steel work was topped off 377 00:17:26,020 --> 00:17:24,790 in April and installation of siding was 378 00:17:29,630 --> 00:17:26,030 begun 379 00:17:32,330 --> 00:17:29,640 at MTF steel position first stage static 380 00:17:34,880 --> 00:17:32,340 test and the b2 position is rapidly 381 00:17:36,800 --> 00:17:34,890 nearing completion fabrication of the 382 00:17:38,810 --> 00:17:36,810 booster support frame is underway and 383 00:17:42,800 --> 00:17:38,820 sheet work on the engine removal 384 00:17:45,200 --> 00:17:42,810 platform has been finished at the b1 385 00:17:46,990 --> 00:17:45,210 position installation of load frames for 386 00:17:49,190 --> 00:17:47,000 the flame deflector is in progress 387 00:17:52,930 --> 00:17:49,200 structural steel and engine removal 388 00:17:55,400 --> 00:17:52,940 platform steel is being received on-site 389 00:17:58,460 --> 00:17:55,410 despite the setback incurred due to the 390 00:18:00,530 --> 00:17:58,470 s2 all system stage explosion March 391 00:18:02,440 --> 00:18:00,540 April and May witnessed the achievement 392 00:18:04,670 --> 00:18:02,450 of a number of vital program goals 393 00:18:07,450 --> 00:18:04,680 including virtual completion of the 394 00:18:10,280 --> 00:18:07,460 Saturn 5 systems development facility 395 00:18:13,550 --> 00:18:10,290 preparation for environmental testing of 396 00:18:15,830 --> 00:18:13,560 the flight systems IU preparation for 397 00:18:19,100 --> 00:18:15,840 simulated high altitude tests of the j2 398 00:18:21,370 --> 00:18:19,110 engine successful acceptance testing of 399 00:18:23,780 --> 00:18:21,380 the first third stage flight stage 400 00:18:26,360 --> 00:18:23,790 initial static firing of the second 401 00:18:29,660 --> 00:18:26,370 stage all system stage marking first 402 00:18:31,940 --> 00:18:29,670 operational use of MTF and culminating 403 00:18:34,640 --> 00:18:31,950 in the major achievement of assembling 404 00:18:37,220 --> 00:18:34,650 for the first time a complete Saturn 5 405 00:18:39,140 --> 00:18:37,230 vehicle at KSC for checkout of 406 00:18:41,540 --> 00:18:39,150 facilities which will be used in 407 00:18:42,080 --> 00:18:41,550 launching the Saturn 5 flight vehicles